House Plans
Main Level Floor Plan
9/7/11
This is what our lot has looked like for the last 6 years
Day 1 Stringing out the foundation
9/8/11
Day 2 Foundation Outlined
Starting to Dig!
Sam's Future Room
Hannah's Future Room (about 12ft lower ;) )
Bre's Future Room
9/12/11 Footing framed in
9 /13/ 2011 Pouring Footings
9/16/11 Framing Foundation
Boys and Toys ;)
9/20/11 Pouring Foundation
9/23/11 Rough Plumbing
9/29/11 Basement Floor Poured
9/30/11 Lumber Delivered
10/3/11 Framing Started
10/6/11 Floor Joist Up
10/7/11
1 Month Mark!
Sub Flooring On